|
Contracts and Claims
Timely articles covering the most
pressing issues facing construction firms in the Midwest
CONCRETE SUPPLIER PREVAILS ON LIEN EVEN
THOUGH MATERIALS SUPPLIED WERE NOT INCORPORATED INTO THE FINAL STRUCTURE
In
a unique Missouri Court of Appeals decision, a concrete supplier was
able to enforce its lien against a project in accordance with R.S.Mo. §§
429.010-429.340, even though virtually none of the materials it supplied
were incorporated into the final structure. Bates County Redi-Mix, Inc.
v. Windler, 162 S.W.3d 98 (Mo. Ct. App. 2005). The case represents a
novel application of the general rule which provides that only materials
that ‘went into’ or were ‘used in’ construction of the property are
lienable. E.g, Boyer Lumber, Inc. v. Blair, 510 S.W.2d 738, 745 (Mo. Ct.
App. 1974).
This unusual situation arose when the concrete supplier, who apparently
provided perfectly good-quality concrete, was not paid because the
concrete subcontractor allegedly poured the concrete foundation
improperly and the owner required the defective foundation to be totally
demolished and removed from the site. The concrete supplier was not paid
and accordingly filed its mechanic’s lien and a suit to enforce it.
Bates, 162 S.W.3d at 100.
The trial court held that the concrete supplier was not entitled to a
mechanic’s lien because the concrete was removed from the property
entirely and was not incorporated into the final structure. Id. at 101.
The concrete supplier appealed and the Missouri Court of Appeals
reversed the trial court’s decision. The Court of Appeals went into a
detailed analysis of the case law in the context where materials are not
incorporated into the final structure and where work is destroyed during
construction. The Court of Appeals concluded that suppliers of only
material (that do not perform work on the project) should be protected
when they provide acceptable materials and those materials are ruined by
others during construction. Accordingly, the Court of Appeals held that
the concrete supplier was entitled to a mechanic’s lien against the
property. Id. at 108.
The court found its case to be distinguishable from other Missouri
cases, which have held that only materials actually used or consumed in
the construction process and which benefited the property were lienable.
For example, in Shine’s Executrix v. Heimburger, the court ruled that a
materialman was not entitled to a mechanic’s lien for bricks used in a
building that was destroyed by high winds during construction. 60 Mo.
App. 174 (Mo. App. 1895). However, the materialman was also the
subcontractor hired to build the structure; thus, the court ruled that a
subcontractor is required to look at the terms of contract between the
owner and the general contractor, and should therefore bear the loss in
the absence of a contract provision allocating the risk to the owner.
Id. at 184.
The court in Bates reasoned that the requirement that the material be
used in the property for a lien to attach was not a statutory necessity.
Rather, it was a factor used by the Shine’s Executrix court in
determining whether equity should allow such a lien. Bates, 162 S.W.3d
at 103. In this case, however, the court reasoned that the materialman
had no contractual relationship with the owner and so could not
contractually shift the risk. Id. at 107.
In Davidson v. Fisher, a materialman was also precluded from asserting a
mechanic’s lien for materials supplied to a construction project. 258
S.W.2d 297 (Mo. Ct. App. 1953). However, in that case the court ruled
that there was not enough evidence to find that the materials were used
in the construction process at all. Id. at 302. A similar result
occurred in Kansas City Elec. Supply Co. v. Bomar Elec. Co. when the
court also did not find enough evidence that the materials supplied were
ever used. 581 S.W.2d 411, 413 (Mo. Ct. App. 1979). The court in Bates
easily distinguished these cases from its own facts, finding that there
was no disagreement that the materialman’s concrete was actually
utilized in the completion of the property’s foundation before it was
destroyed. 162 S.W.3d at 104.
The court did find significant similarity to the facts in Boyer. In that
case, the plaintiff supplied materials for a house that was destroyed by
a fire during construction. The court granted the plaintiff a lien that
included the value of material that was at the site but that was burned
before it was ever installed. The court concluded that the material was
“nevertheless ‘consumed’ in the sense of being used or depreciated
before it could have been incorporated into the structure,” thus
qualifying it for a lien. 510 S.W.2d at 747. The court found Boyer to be
the most similar to its own facts because it involved a materialman,
rather than a contractor or subcontractor, and the material was
destroyed and removed. Bates, 162 S.W.3d at 105.
The court further established that the general requirement that the
materials be used in the property is based on a policy of preventing
contractors from obtaining supplies from materialman and then secretly
transporting them to different construction sites. Id. at 102 n.5
(citing State v. Gregory, 71 S.W. 170, 171 (Mo. 1902). Finding that
policy inapplicable, id. at 104, it also noted the general policy in
Missouri that mechanic’s lien statutes are to be construed as favorably
to materialmen as their terms allow. Id. at 107 (citing Refrigeration
Supplies, Inc. v. J.L. Mason of Mo., Inc., 872 S.W.2d 105, 107 (Mo. Ct.
App. 1994)).
The court concluded its analysis after recognizing the familiar
principle that when one of two innocent parties must suffer a loss
caused by an independent wrongdoer, the loss should be shifted to the
party that gave the wrongdoer authority to commit the harm. Id. at
107-08 (citing Henry & Coatsworth, Co. v. Evans, 10 S.W. 868, 872 (Mo.
1889)). Applying that principle, the court held that, though both
parties were innocent, the owner was in a better position to accept the
risk because the owner hired the contractor and could oversee his work.
Id. at 108. Finally, the court acknowledged that since the function of
the mechanic’s lien law was to encourage materialman to extend credit to
land so that improvements will be made, the best result was for the
innocent plaintiff to be entitled to a lien, even for improperly
installed materials that are later removed from the land.
|