|
Contracts and Claims
Timely articles covering the most
pressing issues facing construction firms in the Midwest
Getting Adjustments When Material
Prices Increase Requires Planning
When prices of construction materials
fluctuate wildly as they did with steel in 2004, a question
naturally arises in specialty contractors’ minds: Are we entitled to
get any price adjustment to our fixed-price contracts if major
material prices go up too much? The unsatisfying answer to this
question is: It depends.
As a rule of thumb, specialty trade contractors that have not gone
out of their way to negotiate a well-written force majeure contract
provision will be legally entitled to price adjustments in an
extremely limited number of cases. A white paper titled “Force
Majeure,” published by the American Subcontractors Association (ASA),
explains:
Courts will excuse failure to perform a contract due to a force
majeure event, but only if the circumstances fit within the
narrowly-defined doctrines of “impracticability,” or if the contract
has an express provision dealing with force majeure events, commonly
called a “force majeure clause.” In fact, the reason to include a
force majeure clause in a written contract is because the law of
impracticability is so narrowly defined that it provides little
protection from unexpected events.
The point about impracticability is that a specialty contractor
would have a hard time convincing most judges that any increase in
prices made its execution of the contract “impracticable.” Courts
would more likely see a large increase in material prices as a risk
inherent to the business of construction than as an unforeseeable
(and excusable) event preventing the specialty contractor from
performing its work at the agreed-upon price.
ASA’s white paper suggests that the specialty contractors that want
adjustments for large price increases are better off proactively
seeking contract language that entitles them to equitable price
increases rather than simply relying on the law. A well-written
force majeure clause that explicitly gives the specialty contractor
more rights than the legal doctrine of “impracticability” would
provide better protection.
Negotiating an effective force majeure clause is the challenge for
specialty contractors to meet if they want assurance of equitable
price adjustments. ASA’s white paper points out several factors to
keep in mind when approaching this task:
· The force majeure clause needs to explicitly rebut the legal
presumption that the specialty contractor is entitled to adjustments
only when work is “impracticable.”
· Force majeure language that specifies a measurable condition as
qualifying the specialty contractor for an adjustment, such as a
material price increase of 20 percent, likely will be more effective
than vague language such as a “major” increase in material prices.
· Most industry model documents for fixed-price contracts do not
contain language giving subcontractors the right to equitable price
adjustments.
· Many force majeure clauses limit the specialty contractor’s
adjustment to an extension of time but are silent on, or deny, price
adjustments.
Learn more about force majeure clauses. Visit ASA’s Web site at
www.asaonline.com and click on “Stand Up! for Subcontractors” or
call ASA at (703) 684-3450.
|