|
Contracts and Claims
Timely articles covering the most
pressing issues facing construction firms in the Midwest
CONTRACTING CONSIDERATIONS: Some things to
consider when entering into a construction contract
J. Nick Badgerow
Risk
allocation is a fundamental consideration in contracts. As a general
proposition, the parties to construction contracts will seek to
include provisions that limit and distribute their respective risks,
duties, responsibilities and liabilities. Such provisions can be
unreasonable in their attempts to shift responsibilities from one
party to another, and should, therefore, be scrutinized very closely
during contract formation and negotiation. Even where express
contract provisions are provided, the law generally imposes implied
warranties, duties, and responsibilities on the parties. Owner
duties and responsibilities that have arisen in recent disputes
include:
1. Funding the work.
2. Providing site surveys.
3. Securing and paying for easements.
4. Warranting the plans and specifications.
5. Warranting owner furnished materials.
6. Disclosing superior knowledge.
7. Acting on clarifications and changes.
8. Interpreting the documents.
9. Cooperating with the contractor.
DISCUSSION
1. Funding the work
Some would list this as the owner's first responsibility to the
contractor, and it is probably the primary area of disputes between
owner and contractor. In the case of a public bid, if the funding
source had not been properly secured, it is at best unfair to those
contractors who had taken the time and expended the energy (and
money) to bid the project. Once the project is underway, one of the
owner's primary responsibilities, as far as the contractor is
concerned, is to secure funds to allow payments as prescribed in the
contract. Related issues include:
(a) The timing of payables
Payments to the contractor are typically made after receipt of each
invoice within the time period specified, or within the requirements
of appropriate legal statutes. The contract language itself often
determines which takes precedence. If the contractor has met the
necessary requirements, the owner can become responsible for
subsequent delay and possibly consequential damages, such as
interest charges or delay damages.
Most if not all of HCG’ s cases involve disputes over owner partial
payments, late payment or non-payments to contractors and/or
designers.
(b) Rates and amounts corresponding to the actual job progress
If materials can be substantiated to be properly stored on the site
and/or installed in-place in an acceptable manner considering all
project requirements, the owner will typically pay for those
materials. An alteration of the process by the owner for convenience
may create a hardship on the general and subcontractors which may
entitle them to compensation. On the other hand, contract
abandonment and termination cases often involve disputes over the
reconciliation between the aggregate amount of material delivered,
installed and paid-for, and the aggregate uninstalled amount of
material remaining on-site. It is not uncommon for materials to
disappear after delivery to the site.
(c) Contingency for changes
Change orders are a normal part of the construction process. As
such, the owner has an obligation to anticipate their occurrence.
Public project funding will incorporate some additional percentage
(often 5% to 7%) of the project bid amount to be budgeted to fund
legitimate changes as they occur. Responsibility for the delay in
the owner’s response to proper contract changes that results from
lack of, or late availability of, funds will often rest with the
owner.
2. Providing site surveys
It is the owner's responsibility to provide complete and accurate
relevant data, as may become necessary for correct installation of
the work. The contractor is typically responsible for the correct
layout and execution of the work.
(a) Establishment of property lines
The most basic information provided by the owner includes the
project property lines, or at least the contract limit lines within
which the contractor has the right to operate. A number of disputes
and litigation cases have involved damage issues and claims
resulting from inaccurate existing data or the improper layout of
property lines.
(b) Site material composition
If excavation is required, geo-technical data describing the soil
composition that will have to be dealt with is a fundamental
prerequisite. The interesting corollary here is that the boring and
soils information should be given in locations properly relevant to
the construction. If the boring information around the perimeter of
a foundation indicates dry gravel, with a low water table, and no
information regarding the soils characteristics is given within the
foundation area, the contractor may assume dry gravel with no water
in the way of the excavation exists throughout the entire foundation
construction. When either rock or unstable soil is subsequently
encountered while excavating the interior portions of the foundation
(where no specific information had been given), the contractor may
be entitled to additional compensation.
(c) Baselines and benchmarks
The contractor is most often responsible for the layout of the work
from baselines furnished by the owner. These data should be
physically located on the site, and the owner assumes responsibility
for and/or warrants their correctness. If the project is then
correctly laid out by the contractor relative to the baselines and
benchmark, errors in the project layout transmitted from incorrect
baseline or benchmark information would typically fall to the
owner's account. Of course, the A/E’s could bear some liability to
the owner for such issues.
(d) Utility locations
The owner is typically responsible for providing accurate locations
of all existing utilities. Locations of telephone lines may be
necessary to tie-in new building services or may be necessary to
prevent accidental interruption. Correct sanitary and storm line
locations and elevations are critical to the design of underground
drainage systems and tie- ins. Invert elevations are also necessary
to allow proper estimates of the amount of excavation and backfill
for the respective lines. If the invert elevation indicated on the
drawings is incorrect, additional excavation may require shoring or
greater trench width – all at increased cost to the contractor. If
this is due to an improper representation on the drawings of the
subject utility location, the owner will often pay for the increased
costs.
(e) Effects of adjacent properties
The relationship of adjacent properties may be significant to the
construction on the site. An important piece of information that may
not be disclosed in the contract documents and may not be readily
apparent in a pre-bid site investigation by the contractor, for
instance, are the drainage characteristics of a surrounding
property. If surface water from several acres of land drains into a
swale that creates an active watercourse through the site that lasts
several days each time it rains, the responsibility for resulting
downtime, additional drainage requirements, and rework of the
affected areas would likely rest with the owner.
3. Securing and paying for easements
(a) Site access
The contractor typically expects to have access to the site, even if
such access is limited or restricted, as may be the case when
working within a military complex, a security area of a
manufacturing facility, or some similar environment, and the
particulars should be made known to the contractor prior to the bid.
On the other hand, the contractor should consider the potential lost
time and attendant costs associated with site access. If any type of
access restrictions were not made clear prior to the commencement of
the work and are not apparent in a reasonable pre-bid site
investigation, the contractor will probably not be expected to carry
the associated resultant additional financial burden.
(b) Agency approvals
It is often the owner's responsibility to secure all agency
approvals prior to the start of work. In the absence of any noted
exceptions in the contract documents, the contractor has the right
to expect that such administrative matters have been taken care of.
Even when the contractor is responsible for securing and paying for
the building permit, as is usually the case, this responsibility
amounts to a formality requiring a small amount of clerical
paperwork and a payment to the jurisdiction in which the project is
located. The contractor has the right to expect that, by the time
the building permit is applied for, all building code requirements
have been met by the design, and the permit procedure should not
require any effort beyond a simple filing. If any delays in securing
the building permit result from code noncompliance of the design,
the owner may be responsible for the resulting costs.
4. Warranting the plans and specifications
The owner warrants the adequacy of the plans and specifications on
many projects and, therefore, bears the responsibility for any
defects or deficiencies in them. Such defects can exist in many
forms, but tend to fall into the two categories: product and time.
Most defective specifications problems involve the inaccuracy of the
technical specifications. Time, then, most often becomes a
consequential consideration related to the failure of the contract
to provide the technical requirements accurately and completely.
5. Warranting owner furnished materials
Where the owner furnishes material and/ or equipment to the
contractor for use in the work, there is a warranty that these items
will be suitable for their intended purpose. Beyond the fundamental
compatibility of materials, the owner is also responsible for the
timing and coordination of the respective items in the same manner
and extent as every other subcontractor and supplier. Shop drawings
and other coordination information should be submitted and
distributed correctly and in a timely manner, and material
deliveries should be made within the requirements of the progress
schedule.
6. Disclosing superior knowledge
The owner has a duty to disclose superior knowledge to the
contractor that may directly or indirectly relate to the work, where
that knowledge is either unknown by, or has not been made available
to, the contractor. For example, if the boring and soils data did in
fact exist for the interior portions of the construction, but the
data was intentionally left out of the contract, the owner may well
bear responsibility for the added cost incurred by the contractor in
dealing with the unstable or inappropriate sub-surface materials.
Likewise, where the owner's superior knowledge of a factor, such as
the unavailability or inadequacy of a specified material, would lead
to reduced costs, improved efficiency, or simply an earlier
disclosure of a problem, the owner has an obligation to so advise
the contractor.
Allegations relating to whether or not the owner knew or should have
known that the project could not be built in the time specified in
the contract commonly refer to the owner’s “superior knowledge.” If
the general contractor informed the owner that, in his judgment, the
project could not reasonably be built in one-year, the owner was
obligated to pass that contractor’s unsolicited opinion on to the
other bidders.
7. Action on clarifications and changes
Construction contracts, whether produced by and for a private owner
or public agency, recognize the need and importance of timeliness
with respect to issuing clarifications and reviewing change orders.
This is an acknowledgment that change orders can interfere with and
disrupt the orderly sequence of the work and that they should be
resolved as quickly as possible to minimize their potential direct
and consequential impact on construction.
The process of anticipating, identifying, pricing, negotiating and
executing changes, change orders and change directives is perhaps
the most prominent thread through our construction disputes. And, it
is a process that exposes human frailties and faults in virtually
all forms and varieties. Acts of negligence, greed, ignorance and
laziness are not uncommon.
8. Interpretation of the documents
Although the architect normally researches and prepares
recommendations for technical matters relating to design, when
involving quality, cost and/or time, these corrections, changes, and
interpretations are communicated to the owner who often controls the
final disposition on the matter. Actual authority for some portion
of the process may rest with the architect. Because no direct
contractual tie exists between the architect and the contractor,
however, responsibility for the architect's performance in these
situations rests with the owner.
9. Cooperating with the contractor
Even when not expressed in the contract, it is generally understood
that the owner has an implied duty to cooperate with the contractor
to the best of his ability, and not to impede, hinder, obstruct, or
interfere with the work. The same concept applies to the contractor.
Although this sounds simple, its success or failure often boils down
to the personalities involved. Both parties are focused on the
traditional objectives of time, cost and budget, but to differing
degrees and from different perspectives. A consistent theme in
disputes is the disintegration of cooperation as a result of
conflicts between owner and contractor over the achievement of time,
cost and quality objectives.
The main point to consider is that all contracts, including
construction contracts, impose obligations on both parties, and each
party would do well – before entering into the contract – to
allocate those obligations and duties in a fair manner, and then to
understand and comply with those obligations once the contract has
been made.
|